Airport expansion EIR review periodDIVISION 13. ENVIRONMENTAL QUALITY › CHAPTER 2.6. General

Key provisions · Claude summary, not statute text

Draft EIRs for certain publicly owned airport expansions require a 120-day minimum review period.

  • Triggering projects. The rule covers expansion or enlargement of a publicly owned airport requiring acquisition of tide and submerged lands or other public trust lands, or any interest in them. § 21091.5
  • Minimum review period. The public review period for the draft EIR must be not less than 120 days, notwithstanding § 21091(a). § 21091.5

Paraphrased from the statute text; each point cites its subdivision. Check the text before relying on it.

ClaudeGreen text is a summary heading written by Claude to help navigate. It is not statute text; the statute text is in black.

§ 21091.5

Notwithstanding subdivision (a) of Section 21091, or any other provision of this division, the public review period for a draft environmental impact report prepared for a proposed project involving the expansion or enlargement of a publicly owned airport requiring the acquisition of any tide and submerged lands or other lands subject to the public trust for commerce, navigation, or fisheries, or any interest therein, shall be not less than 120 days.

Source. California Code text from the Legislature's bulk download (the same data as leginfo), reproduced character for character (spacing normalized). Current page on leginfo ↗

History. (Added by Stats. 2001, Ch. 534, Sec. 2. Effective January 1, 2002.)