The section exempts defined small drinking water and sewer projects from CEQA, subject to environmental conditions and labor standards, until January 1, 2032.

  • Exempt project benefits. CEQA does not apply to a qualifying project that primarily benefits a small disadvantaged community water system or state small water system by improving water quality, supply, or reliability, encouraging conservation, or serving existing residences with contaminated or failing water. (b)(1)
  • Covered project types. A project is limited to specified drinking water facilities of defined size, such as wells up to 250 gpm, tanks up to 250,000 gallons, and pipelines in road rights-of-way, or sewer service to a disadvantaged community. (a)(6)(A)
  • Excluded facilities. Facilities built primarily to serve irrigation or future growth, and facilities that dam, divert, or convey surface water, are not projects. (a)(6)(B)
  • Environmental conditions. The project must not affect wetlands or coastal sensitive habitat, involve unusual circumstances, sit on a listed hazardous waste site, or change a historical resource, and its construction and cumulative impacts must be addressed. (c)
  • Public agency workforce rule. For public agency projects, entities must commit to using a skilled and trained workforce to be prequalified or awarded contracts, unless a listed project labor agreement exception applies. (d)
  • Private project labor rules. For private projects, the applicant must certify prevailing wage compliance (or public work status) and use of a skilled and trained workforce, with monthly compliance reports. (e)
  • Penalties. Failure to report incurs a $10,000 monthly civil penalty, and contractors not using a skilled and trained workforce face $200 per day per worker, assessed within 18 months of completion. (e)(2)(C)
  • Consultation and notice. The lead agency must contact the state board about federal assistance effects before claiming the exemption, and must file a notice of exemption when approving the project. (b)(2), (f)

Paraphrased from the statute text; each point cites its subdivision. Check the text before relying on it.

ClaudeGreen text is a summary heading written by Claude to help navigate. It is not statute text; the statute text is in black.

§ 21080.477 subdivisions

Source. California Code text from the Legislature's bulk download (the same data as leginfo), reproduced character for character (spacing normalized). Current page on leginfo ↗

History. (Amended by Stats. 2025, Ch. 24, Sec. 9. (SB 131) Effective June 30, 2025. Repealed as of January 1, 2032, by its own provisions.)

Cited by, in this navigator. Pub. Resources Code § 21080.31, Pub. Resources Code § 21080.48

See these connections on the network →

Other sections cited. 19 sections outside this navigator are underlined in the text; hover one for its leginfo link; the References tab lists them all.

Statute text comes from the California Legislative Information page saved for this section; spacing and line breaks are normalized and every other character is reproduced as published. Check leginfo for any amendment made after the page was saved. Not legal advice.