The § 21080.1 determination for § 21065(c) projects is due within 30 days of a complete application.

  • 30-day deadline. The § 21080.1 determination must be made within 30 days of the lead agency receiving and accepting a complete application. § 21080.2
  • 15-day extension. The period may be extended 15 days upon consent of the lead agency and the applicant. § 21080.2

Paraphrased from the statute text; each point cites its subdivision. Check the text before relying on it.

ClaudeGreen text is a summary heading written by Claude to help navigate. It is not statute text; the statute text is in black.

§ 21080.2

In the case of a project described in subdivision (c) of Section 21065, the determination required by Section 21080.1 shall be made within 30 days from the date on which an application for a project has been received and accepted as complete by the lead agency. This period may be extended 15 days upon the consent of the lead agency and the project applicant.

Source. California Code text from the Legislature's bulk download (the same data as leginfo), reproduced character for character (spacing normalized). Current page on leginfo ↗

History. (Amended by Stats. 1984, Ch. 586, Sec. 1.)

Cites, in this navigator. Pub. Resources Code § 21080.1

See these connections on the network →

Other sections cited. 1 sections outside this navigator are underlined in the text; hover one for its leginfo link; the References tab lists them all.

Statute text comes from the California Legislative Information page saved for this section; spacing and line breaks are normalized and every other character is reproduced as published. Check leginfo for any amendment made after the page was saved. Not legal advice.